Preventative Maintenance (PM)
CES+ Classifies a Preventative Maintenance as the following:
Projectors and Servers:
-
Remove the projector covers and the air filters will be cleaned or replaced (if onsite at the time of the PM)
-
The Optical system is then inspected and cleaned
-
The internal and external panels are cleaned and inspected
-
The Liquid cooling system is inspected and flushed (Per manufacturer's recommendation if coolant is onsite at the time of the PM)
-
The projector boards are removed to clean the card cage
-
Once the machine is reassembled all the security tamper switches are tested and the project boards are married
-
The machine will be leveled if necessary
-
The cinema servers panels are removed and cleaned
-
An internal inspected will be done
-
Server motherboard and video card batteries are replaced per manufacturers recommendation (Hardware cost to be covered by client)
-
Update the projector and server to the current version
-
The projected images are aligned with standardized framing charts to restore focus to your presentation
-
The colors and light levels are calibrated to studio specifications
-
All macros are tested to verify your system is properly operating
Sound
-
Clean the exterior of the sound rack
-
Clean the amplifiers
-
Clean the sound processor
-
Pink noise will be run through each amp and speaker to test for proper signal path and output frequency range.
-
A visual inspection of each speaker is done (If possible without a ladder).
-
Upgrade the audio system software to the current version.
-
Microphones are placed in the auditorium and a full audio calibration is performed. The audio system is thoroughly tested with DCP content.
Emergency Visit (EM)
CES+ classifies an Emergency Visit as the following:
When there is a screen down and the ces+ support center cannot fix this issue remotely we will dispatch a certified technician for an Emergency Call